PMI PMI-RMP Question # 67 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

During a risk reassessment workshop with the project team and some external stakeholders, two key external stakeholders are overemphasizing the impact of a few project risks. This has led to a conflict.

How should the risk manager handle this situation?


A.

Request for a skilled facilitator to help resolve conflicts that have arise.


B.

Refer to the team’s ground rules on how to resolve conflicts.


C.

Run a sensitivity analysis to check which risks have the most impact.


D.

Use the assumption analysis techniques to validate the assumptions.