PMI PMI-RMP Question # 69 Topic 7 Discussion

PMI-RMP Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

In the middle of a project to improve internal workflows, the team realizes that some previously identified challenges, such as lack of stakeholder engagement, have diminished. However, the risk manager determines that concerns related to resource availability and regulatory compliance are becoming more significant.

Which measures should the risk manager implement?


A.

Concentrate on monitoring only high-visibility risks to conserve resources.


B.

Focus on tracking the risks identified at the project's start to maintain consistency.


C.

Reassess risk priorities carefully and update the risk register on a regular basis.


D.

Delegate all monitoring responsibilities entirely to individual team members for efficiency.