PMI PMI-RMP Question # 71 Topic 8 Discussion

PMI-RMP Exam Topic 8 Question 71 Discussion:
Question #: 71
Topic #: 8

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?


A.

Review and update the project quality management plan.


B.

Conduct a risk assessment process for the critical stage.


C.

Create a more detailed work breakdown structure (WBS).


D.

Add additional time to the delivery plan to cover issues.  