Question #: 9
Topic #: 1

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?


A.

Advise the customer to discuss changes with the product owner.


B.

Document this issue in the sprint backlog for discussion at a team meeting.


C.

Ask the customer to submit a change request to the project sponsor.


D.

Encourage the team to clarify the requests with the customer.