PMI Project-Management-Professional PMP Question # 98 Topic 10 Discussion

PMP Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?


A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach


B.

Explain and communicate the new approach to the project sponsor and key stakeholders


C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders


D.

Communicate with other project managers to see how they manage hybrid projects