Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 1076 Topic 109 Discussion

PMP Exam Topic 109 Question 1076 Discussion:
Question #: 1076
Topic #: 109

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?


A.

Create a risk probability matrix to address the incompatibility.


B.

identify an alternative component in case of incompatibility.


C.

Use the contingency fund to redesign the interface if it is incompatible,


D.

Require the vendor to redesign the incompatible component to fit the system.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.