Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 104 Topic 11 Discussion

PMP Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?


A.

Fast tracking


B.

Resource leveling


C.

Critical chain method


D.

Schedule crashing


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.