Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 67 Topic 11 Discussion

PMP Exam Topic 11 Question 67 Discussion:
Question #: 67
Topic #: 11

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?


A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.


B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.


C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,


D.

Check with procurement to see if there is another previously used contractor who can develop the task.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.