Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 69 Topic 11 Discussion

PMP Exam Topic 11 Question 69 Discussion:
Question #: 69
Topic #: 11

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?


A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.


B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.


C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.


D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.