Question #: 1098
Topic #: 111

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?


A.

Review the project scope to align the project teams


B.

Review the resource management plan to align the project teams


C.

Review the project integration plan to align the project teams


D.

Review the work breakdown structure (WBS) to align the project teams