PMI Project-Management-Professional PMP Question # 1153 Topic 117 Discussion

PMP Exam Topic 117 Question 1153 Discussion:
Question #: 1153
Topic #: 117

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?


A.

Recommend that the product owner reviews the backlog refinement processes.


B.

Recommend that the team reviews the length of the iteration with the stakeholders.


C.

Recommend limiting the work in progress to improve the team’s focus.


D.

Recommend a review of the team members’ individual performances.