PMI Project-Management-Professional PMP Question # 72 Topic 12 Discussion

PMP Exam Topic 12 Question 72 Discussion:
Question #: 72
Topic #: 12

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?


A.

Risk register


B.

Project schedule


C.

Change request


D.

Issue log