PMI Project-Management-Professional PMP Question # 1182 Topic 120 Discussion

PMP Exam Topic 120 Question 1182 Discussion:
Question #: 1182
Topic #: 120

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?


A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2


B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2


C.

Requirements, Requirement 1, Requirement2


D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2