A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?


A.

Ask the project sponsor for assistance in getting the budget back on track


B.

Meet with the project team to analyze the actual cost to determine deviations


C.

Inform the stakeholders that the project will be finished over budget.


D.

Issue a change request including the analysis to increase the budget