PMI Project-Management-Professional PMP Question # 120 Topic 13 Discussion

PMP Exam Topic 13 Question 120 Discussion:
Question #: 120
Topic #: 13

During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?


A.

Revisit the communications management plan and make necessary adjustments


B.

Revisit the scope management plan and note this as a risk


C.

Schedule a meeting with the product owner and finance team to agree on course corrections


D.

Continue developing based on the project management plan and address the issue post delivery