Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 121 Topic 13 Discussion

PMP Exam Topic 13 Question 121 Discussion:
Question #: 121
Topic #: 13

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?


A.

Review the project scope and negotiate with the contractor


B.

Refuse the offer as it is included in the initial project scope


C.

Review the project costs and communicate this to the project sponsor


D.

Submit a change request to approve the offer


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.