After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?


A.

Develop the team members to work as a cross-functional team.


B.

Ask a functional manager to provide the right team members.


C.

Review the project charter to see if the scope can be modified.


D.

Ask the portfolio manager to reassign the project to another team.