PMI Project-Management-Professional PMP Question # 1282 Topic 130 Discussion

PMP Exam Topic 130 Question 1282 Discussion:
Question #: 1282
Topic #: 130

During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?


A.

Let the product go to market and wait for customer feedback regarding quality


B.

Ask the quality manager to include the final user tests in the quality management plan.


C.

Submit a change request to analyze a new set of quality tests


D.

Ask the product manager to include the final user tests in the quality management plan