PMI Project-Management-Professional PMP Question # 102 Topic 14 Discussion

PMP Exam Topic 14 Question 102 Discussion:
Question #: 102
Topic #: 14

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?


A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project


B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful


C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor


D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project