Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 91 Topic 14 Discussion

PMP Exam Topic 14 Question 91 Discussion:
Question #: 91
Topic #: 14

A project manager working on a software development project asked the software development about the status of a task. The developer responded that the task was delivered 1 week ago and mentioned that the delivery was reported via a specific project management software.

What should the project manager do next?


A.

Review the stakeholder engagement plan and communicate which technology is available to develop, transmit, and store project artifacts.


B.

Engage the software developer, let them work with this project management software, and then conduct a train-the-trainer activity to ensure everyone can use it.


C.

Research the project management software to understand how it works, and establish it as the acceptable software to hold the project artifacts.


D.

Review the communications management plan and communicate which technology is to be used to develop, transmit, and store project artifacts,


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.