A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?


A.

Update the project charter with the new requirement.


B.

Add a risk to the risk register.


C.

Add it to the issue log as an ongoing issue.


D.

Review and validate the scope management plan.