PMI Project-Management-Professional PMP Question # 110 Topic 15 Discussion

PMP Exam Topic 15 Question 110 Discussion:
Question #: 110
Topic #: 15

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?


A.

Monitored progress in achieving the business value throughout the project


B.

Asked for additional time to achieve the project goals and increase business value


C.

Increased the number of project resources to ensure attainment of the business value


D.

Reviewed previous projects’ lessons learned and applied them to this project