Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 114 Topic 15 Discussion

PMP Exam Topic 15 Question 114 Discussion:
Question #: 114
Topic #: 15

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.

What should the project manager do?


A.

Create a roles and responsibilities matrix based on the project charter and ask the sponsor to share it with all stakeholders to provide credible authority


B.

Conduct scoping workshops with the project team to create a work breakdown structure (WBS), assign tasks to various entities share this with all stakeholders, and ask the team to complete their tasks as scheduled


C.

Conduct a general meeting with all stakeholders and review and address a list of activities for each of them


D.

Breakdown the situation to identify the root causes for the disagreement and then work with each stakeholder and participating entity on their exact roles and responsibilities


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.