Question #: 1526
Topic #: 154

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?


A.

Escalate the issue to the project sponsor.


B.

Address the issue during the next sprint planning meeting.


C.

Initiate a change request to extend the project end date.


D.

Extend the dates for future project milestones.