Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 137 Topic 17 Discussion

PMP Exam Topic 17 Question 137 Discussion:
Question #: 137
Topic #: 17

A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?


A.

Persuade this stakeholder using emotional intelligence skills to obtain acceptance.


B.

Obtain final acceptance from another stakeholder who is also familiar with the project


C.

Escalate this issue to the project sponsor and ask for support in obtaining final stakeholder acceptance.


D.

Create a project acceptance waiver noting the stakeholder’s concerns so they can be addressed later


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.