Question #: 138
Topic #: 17

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?


A.

Move to a Kanban strategy so that work can be reallocated more easily


B.

Decrease the sprint cycle to the average repriontization request by calculating it in days


C.

Set up a meeting with the project team and ask for their opinion on what to do


D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle