PMI Project-Management-Professional PMP Question # 1761 Topic 178 Discussion

PMP Exam Topic 178 Question 1761 Discussion:
Question #: 1761
Topic #: 178

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?


A.

Move one of the team members to a different protect team


B.

Review the ground rules for collaboration within the team


C.

Report the performance issue to both of the team members' supervisors


D.

Modify the communications management plan and resend it to the team