Question #: 141
Topic #: 18

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?


A.

Encourage frequent small team meetings with two or three team members.


B.

Give up the daily standup and replace it with a daily report


C.

Let the team members decide themselves if they want to join the meeting.


D.

Require all team members to join the daily standup regardless of the meeting time