Spring Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 1848 Topic 186 Discussion

PMP Exam Topic 186 Question 1848 Discussion:
Question #: 1848
Topic #: 186

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?


A.

Submit new user stories to the product owner in order to put documentation in the product backlog.


B.

Introduce a document management tool to support the agile teams in preparing the documentation.


C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.


D.

Add an additional team member to take up the role of scribe for the required documentation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.