PMI Project-Management-Professional PMP Question # 1939 Topic 195 Discussion

PMP Exam Topic 195 Question 1939 Discussion:
Question #: 1939
Topic #: 195

During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager

notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.

How should the project manager handle this situation?


A.

Set up a proper governance structure to ensure functional managers’ requests are processed correctly.


B.

Modify the communications management plan to enable functional managers to add changes to the project.


C.

Follow the project constraints and move forward with the agreed schedule baseline and the cost baseline.


D.

Ask the functional managers to communicate with their peers and emphasize the impact of their requirements.