A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?


A.

Establish mentoring and coaching sessions.


B.

Review the knowledge repository for similar projects.


C.

Schedule the project kick-off meeting immediately.


D.

Meet with the project sponsors to align expectations