Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 11 Topic 2 Discussion

PMP Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?


A.

Seek the sponsor's approval to extend the project schedule.


B.

Set up a meeting to perform a root cause analysis.


C.

Update the issue log and communicate it to the team.


D.

Permanently colocate the team for better performance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.