PMI Project-Management-Professional PMP Question # 164 Topic 20 Discussion

PMP Exam Topic 20 Question 164 Discussion:
Question #: 164
Topic #: 20

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?


A.

Ask the team to work overtime to complete the deliverable on time


B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines


C.

Check the scope to verify if there is scope creep and get the project on schedule


D.

Submit a change request to the project sponsor to change the schedule