PMI Project-Management-Professional PMP Question # 200 Topic 21 Discussion

PMP Exam Topic 21 Question 200 Discussion:
Question #: 200
Topic #: 21

A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?


A.

The deliverables that are performing well and those that need more work.


B.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.


C.

Potential changes to the project's strategy and the feedback from senior executives.


D.

Specialized reports created specifically for the meeting as per directions from the project sponsor.