During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.
What should the project manager do?
A.
Review and update the project management plan to accommodate the delays.
B.
Speak with the project sponsors about changing the project management plan.
C.
Create a change request to increase the cost of resources.
D.
Delay the project until additional resources can be identified.
Chosen Answer: