Cyber Monday Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 2121 Topic 214 Discussion

PMP Exam Topic 214 Question 2121 Discussion:
Question #: 2121
Topic #: 214

During project planning activities, a project manager identifies potential delays in obtaining resources required for a project. This will significantly impact the construction timeline.

What should the project manager do?


A.

Review and update the project management plan to accommodate the delays.


B.

Speak with the project sponsors about changing the project management plan.


C.

Create a change request to increase the cost of resources.


D.

Delay the project until additional resources can be identified.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.