PMI Project-Management-Professional PMP Question # 187 Topic 22 Discussion

PMP Exam Topic 22 Question 187 Discussion:
Question #: 187
Topic #: 22

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches The scope of the project contains a number of unclear requirements.

How should the project manager plan the delivery of the project?


A.

Wait for the requirements to be more clear before any further action is taken on the project


B.

Ignore the unclear requirements and focus on the delivery plan of the project


C.

Escalate the issue of unclear requirements to the management team and wait for final authorization


D.

Break down the requirements and prioritize the requirements into iterative work packages