PMI Project-Management-Professional PMP Question # 198 Topic 23 Discussion

PMP Exam Topic 23 Question 198 Discussion:
Question #: 198
Topic #: 23

A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will

take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6

months.

What should the project manager do to align stakeholders’ needs and expectations?


A.

Work with the stakeholders to create a prioritized backlog and release a roadmap.


B.

Modify the requirements to those that can be completed in 6 months.


C.

Implement fast-tracking and crashing activities to complete the project in 6 months.


D.

Include all stakeholders in daily scrum meetings to keep them informed.