A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?


A.

Create a framework to justify project execution.


B.

Utilize an agile approach for all upcoming projects.


C.

Create a framework to support project success.


D.

Utilize a predictive approach for all upcoming projects.