Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 217 Topic 25 Discussion

PMP Exam Topic 25 Question 217 Discussion:
Question #: 217
Topic #: 25

All project team members refer to the project manager for various decisions. This causes delays for some tasks, as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?


A.

Review the Pareto diagram to identify the source of delays.


B.

Meet with the team in 2 weeks to respond to all of the open tasks.


C.

Consolidate the decision-making authority to remain with the project manager.


D.

Delegate the decision-making authority of some tasks to the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.