Question #: 222
Topic #: 26

While finalizing project management plans, a customer provides the project manager with a new set of quality standards to which the final product must adhere. What

should the project manager do to ensure a smooth delivery of the product?


A.

Involve the client in risk identification.


B.

Agree with the client on acceptance criteria.


C.

Involve the client in a performance gap analysis.


D.

Agree with the client on a new project charter.