Question #: 259
Topic #: 26

A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.

What should the project manager have done differently?


A.

Invited the customer to the daily meetings


B.

Helped the team redefine the MVP


C.

Changed the duration of iterations to deliver more value


D.

Validated the iteration goals with the customer