PMI Project-Management-Professional PMP Question # 231 Topic 27 Discussion

PMP Exam Topic 27 Question 231 Discussion:
Question #: 231
Topic #: 27

A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins

to identify, evaluate, and categorize the stakeholder relationships to the program.

What is the purpose of this process?


A.

Identify all stakeholders who can negatively affect the project.


B.

Incorporate the needs of all stakeholders into the communications management plan.


C.

Incorporate only primary stakeholders into the communications management plan.


D.

Identify all stakeholders who can positively affect the project.