Question #: 232
Topic #: 27

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?


A.

Ask the technical team to revise the requirements, even if it requires extra budget.


B.

Arrange a meeting with the client to request additional time to find a new supplier.


C.

Review the existing service contracts to find an option to help procure the vehicles.


D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.