PMI Project-Management-Professional PMP Question # 235 Topic 27 Discussion

PMP Exam Topic 27 Question 235 Discussion:
Question #: 235
Topic #: 27

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project

and the customer.

What should the project manager do?


A.

Ask the team member to submit a formal change request.


B.

Accept the suggestion as it has no impact on the project.


C.

Ask another team member to validate the impacts of the suggestion.


D.

Reject the suggestion and ask the team member to focus on executing the plan.