Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 236 Topic 27 Discussion

PMP Exam Topic 27 Question 236 Discussion:
Question #: 236
Topic #: 27

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?


A.

Ensure team B prioritizes the dependent activity in iteration three.


B.

Include the dependent activity in the current iteration for team B.


C.

Assign the two critical activities to team B in iteration two.


D.

Cancel the current iteration and reschedule it with the dependent activity.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.