Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 267 Topic 27 Discussion

PMP Exam Topic 27 Question 267 Discussion:
Question #: 267
Topic #: 27

A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring SO many iterations with a risk of not reaching the mandatory delivery date.

Which approach should the project manager use in this situation?


A.

Hybrid approach


B.

Predictive approach


C.

Kanban approach


D.

Agile approach


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.