PMI Project-Management-Professional PMP Question # 240 Topic 28 Discussion

PMP Exam Topic 28 Question 240 Discussion:
Question #: 240
Topic #: 28

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?


A.

Assess and prioritize the impact of the new law on the project plan.


B.

Update the project plan because the law is an obligation for the project.


C.

Minimize the scope to catch the cost and schedule baseline.


D.

Meet the sponsor to ask for additional time and budget increase.