PMI Project-Management-Professional PMP Question # 263 Topic 29 Discussion

PMP Exam Topic 29 Question 263 Discussion:
Question #: 263
Topic #: 29

A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.

How should the project manager address the issue?


A.

Create a self-paced learning plan with the team member during working hours, with checkpoints on learning progress.


B.

Review which tasks the team member would feel more motivated to work on, then assign those tasks to the team member.


C.

Replace the team member with a resource from another team who already has the requisite training and skills needed.


D.

Discuss growth and development needs with the team member and provide learning opportunities accordingly.