Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 27 Topic 3 Discussion

PMP Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?


A.

Explain to the stakeholder that any modifications require additional budget


B.

Review the missed program deliverables with the project team


C.

Review the project charter for the project approval criteria


D.

Speak with the team's manager to get extra hours from the team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.