Question #: 266
Topic #: 30

A customer is concerned with the quality of the product delivery, as the production deployment is approaching. What should the project manager do next to ensure acceptance of the deliverables?


A.

Test product integration in accordance with the requirements.


B.

Evaluate the quality checklist for product compliance.


C.

Review the approved exit criteria for the product.


D.

Verify the production budget before advancing the product.